BAYFRONT AT A GLANCE

  • 480-bed private hospital
  • 75,000 ft2
  • Over 3,000 employees
  • (4) York chillers
  • 2,575 tons installed cooling capacity

APPROACH

  • Convert plant to Integrated Primary/Secondary® design
  • Reconfigure tertiary pumps to alleviate system pressure problems and eliminate wasted energy
  • Add VFDs to all building pumps to eliminate wasted pump energy
  • Design and install PLC based adaptive control algorithms to ensure maximum chiller loading, optimal control of all CHW pumps and proper balance of cooling towers and chillers

IMPLEMENTATION

  • CEO ® system connected directly to JCI Metasys system via BACnet IP protocol, allowing tekWorx to gather real-time data on temperatures, flows, etc., and to fully control all plant equipment
  • Failover sequence developed and implemented to address control redundancy
  • No plant downtime during the course of this project
  • All major equipment remained in operation during commissioning

RESULTS

  • Manually operated system operating at 1.1kW/ton is now a real-time adaptive control system operating at .75 kW/ton
  • System experiences much less wear and tear
  • Operators are now freed up to perform other important tasks
  • CEO® User Interface has provides the staff with better insight into the system for diagnostics and trouble shooting

To learn more about this study and to see how tekWorx can help to optimize your plant, visit www.tekWorx.us