Private TN College Maximizes Cooling Efficiency with Xpress

Hassle-free retrofit dramatically reduces consumption, cuts maintenance costs and extends equipment life 

Facility Bio

  • Nashville, TN
  • CHW plant serves over one million sqft of laboratory space and medical research facilities
  • 3,600 tons cooling capacity

Situation

  • Traditional Primary-Secondary hydronic system
  • Low CHW ΔT, high kW/ton
  • JCI Metasys building automation system, no optimization sequence

Solution

  • Convert to full variable flow using Integrated Primary- Secondary® system design
  • Install DPTs
  • Implement tekWorx Xpress optimization solution and Energy Efficiency Dashboard 

 

Results That Exceed Client Expectations

Financial Savings

  • $84,000 in annual energy savings
  • 2.5 year project payback

Energy Impact

  • Over 1,4000,000 kWh saved annually
  • .20 kW/ton efficiency improvement

Operational Benefits

  • Improved CHW flow enabled higher building space temperatures
  • Pumps running in most efficient range, reduced wear and maintenance
  • Real-time data on all CHW equipment makes troubleshooting faster and less expensive
Still Have Questions?

Start saving on cooling costs.

Calculate your savings instantly

We are the chilled water plant optimization experts

tekWorx optimization solutions consistently save faciliites 20-40% in annual energy costs. We'd love to help your facility do the same. Get in touch!

Approachable Expertise ®
4538 Cornell Road
Cincinnati, Ohio 45241
1-513-533-4777
[email protected]
© 2020 tekWorx. All right reserved. Privacy Policy